Water Meter Set Fees
Current fee for meter set for a 1” is $398.00.
The meter set for a 1-1/2”, 2”, 3”, 4”, 6” is calculated on actual time, materials plus indirect costs.
Each new connection to the water system shall pay as part of their connection charges their equitable share of the cost of the system according to the following schedule.
Residential
The current Water System Development Charge for a single family residence is $5,766.00.
Commercial
The commercial building water system development charge (SDC) is calculated on the size of the meter necessary for the building.
-
The Water SDC for a 5/8” meter is $7,749.00
-
The Water SDC for a 1” meter is $14,416.00
For meters larger than a 1” meter the SDC will be determined on each individual case based on the projected amount of usage and peaking expected from the customer. These charges shall reflect residential equivalence (RE) values used for individual residential customers.
Multifamily
In multifamily developments each unit shall be charge 77% of the current system development charge (SDC) for water meters up to 2 inches. For larger than 2 inches the SDC shall be determined on each individual case, based on the projected amount of usage and peaking expected from the customer. These charges shall reflect residential equivalence (RE) values used in individual residential customers. There shall be only one water meter installed for each building housing multiple residential units. The current fee is $4,439.82 per unit.
Irrigation
Current Irrigation Fees are:
-
The irrigation SDC fee for a 5/8” meter is $4,444.00
-
The irrigation SDC fee for a 1” meter is $11,110.00
1 ½” or larger to be determined on each individual case, based on the projected amount of usage and peaking expected from the customer.
These charges shall reflect residential equivalence (RE) values used for individual residential customers.
Also, you can request a Large Meter Connection Charge handout from the Permit Center.
General Water Requirements
For meters larger than a 1” meter the SDC will be determined on each individual case based on the projected amount of usage and peaking expected from the customer. These charges shall reflect residential equivalence (RE) values used for individual residential customers.
The owner of the premises to which the water service is attached shall be responsible for the payment of all connections, shutoffs, turn on, service charges and liens. Monthly availability fees begin as soon as the water meter is installed.
Property owners are responsible for all leaks or damage due to leaks from privately installed and owned water lines. The property owner shall install and maintain at his own expense all water service from the water meter to the place of use.